  • Variation of technical solutions for foundations and reinforcement of the weak base of the distribution center building in karst conditions

    The installation of foundations of production facilities on sites subject to karst formation and suffusion processes in conditions of weak soils is a serious problem in the design and construction of large distribution centers. In such a situation, it is necessary to calculate the load-bearing elements of the building for the effect of the lack of reaction of the base under the sole of the foundations on a site with a diameter of 3.0 m, located in the most unfavorable places from the point of view of structural work. Such unfavorable locations of a karst sinkhole can be determined by digitally constructing "influence functions" and obtaining "envelope" diagrams of pressure on the base, foundation sediment, and structural reinforcement. If the maximum allowable precipitation of the foundations obtained by calculation is exceeded, it is possible to strengthen the soils by layer-by-layer recycling, which will allow reaching the normative indicators.

    Keywords: karst formation, suffusion, sinkhole, calculated combination of loads, special combination of loads, reinforcement, foundation sedimentation, ground pressure

  • Features of calculation and reinforcement of the foundations of the distribution center building in conditions of weak soils

    The cargo turnover of modern distribution centers of network operators reaches hundreds of thousands of tons per year. The technological load on the floors in the warehouse part of the building is 8-10 t/m2 (80-100 kPa), on the floors – up to 2.4 t/m2 (24 kPa). These loads transfer significant pressure through the foundations of the frame to the ground, which, with large sole sizes and mutual influence, increases the lower boundary of the compressible thickness and, as a result, the draft of structures. In the presence of weak soils at the base, precipitation reaches exorbitant values. The situation is aggravated by the high groundwater level, which also increases the sedimentation of foundations. The article presents and analyzes options for solving the problem by strengthening the base by compacting the top layer and cementing it to different depths depending on the pressure and construction of the foundation.

    Keywords: reinforcement of the base, recycling, permissible calculated precipitation, calculated soil resistance

  • Issues of sufficiency of engineering and geological surveys on the part-time territory for the installation of the foundations of power floors and foundations of the logistics center

    The loads on the power floors and column foundations of modern logistics centers can reach 6-9 t/m2 and 1000 t, respectively. At the same time, the step of the grid of exploration wells in the mined areas does not allow reflecting on the geological sections the exact geometry of the occurrence of weak, untreated soils of backfilling pits. The use of a method for strengthening man-made soils by pressing in prefabricated prismatic piles made it possible to compensate for the missing information from engineering and geological surveys by controlling the forces of indentation and thus determining the occurrence marks of more durable foundation soils.

    Keywords: engineering and geological surveys, the territory being worked on, man-made soils, soil reinforcement with piles, geological section

  • Features of the arrangement of the abutments of the projected driveways of industrial enterprises to the existing landscaping

    The paper considers the problem of the arrangement of the abutments of newly erected driveways and roads of agricultural production enterprises to existing roads and driveways. When connecting the "pies" of the roadways of the projected driveways with the existing landscaping, it is necessary to solve the problem of preventing cracking in the coating at the places of the thickness difference of the structural layers. In the article, this problem is solved both from the technical side, by ensuring the joint work of the new and existing road structure, and from the normative one by assigning the projected passage to the IVB category road, in accordance with SP 37.13330.2012, which allows the construction of a road with curbs without curbs and, as a consequence, without storm sewers and sewage treatment plants.

    Keywords: road network, cadastral boundaries, the design of the widening of the passage, the technical solution of the junction of roads, transverse profile